Promulgated under President Order Hua-Tsung (1)-Yi-Tzu No. 09400192971 on November 30, 2005

Article 26,44 were amended and promulgated under the President Order Hua-Tsung (1)-Yi-Tzu No. 09800129141 on May 27, 2009

Chapter 1 General

Article 1

This Act is established to effectively administrate industrial use explosives, to prevent hazard and preserve public safety.

Article 2

The so-called industrial use explosive materials (named as explosive material in this Act) listed in this Act, are the materials listed in the following paragraphs for mining, exploration, sand and gravel excavation, civil engineering, construction and blasting artifact.

1.      Explosive products used for blasting works, including on-site bulk blasting agents.

2.      Initiation products used for priming, initiation, launching, including various types of detonators, safety fuse, detonating cord, primer cap, ignition cap, delay detonators and propellant.

3.      The raw materials used to manufacture low and high explosives listed in paragraph 1 and 2 in this article.

The on-site bulk blasting agents described in paragraph 1 of this article are mixtures of non-explosion materials and chemicals which are mixed on-site through special design equipments and charge into blast hole immediately after mixing and need to be initiated by proper initiation system.

The items of industrial explosive described in paragraph 1 of this Article shall be promulgated by Central Governing Agency.

Article 3

The contracting organization described in this act means the organization through which a project is contracted to other governmental or private organization for execution.

Article 4

The governing agencies as referred hereunder shall be Ministry of Economic Affairs at Central Government, Municipal Government at Municipal City under the direct jurisdiction of the Central Government and County and City Government at County and City.

Article 5

The jurisdiction of governing agencies are listed as follows:

1.      Central Governing Agency:

a.       The establishment, revision, abolishing and interpretation of the explosives administrative regulations.

b.      The establishment of permission, registration and abolishing of explosive products manufacturing and selling.

c.       Permission and management of explosives alienation, lending.

d.      The required procedures according to company law and other regulations related to factory management and assistance.

e.       The erect of distribution office for explosive sales, import and export of explosives, safe keeping in other magazine, disposal procedures, permission, monitoring and management for the establishment of magazine.

f.        The procedures for the issue of certificate for explosives purchasing quota and transportation.

g.       The monitoring, inspection and emergency measures for explosives and their manufacturing, sales and usage.

h.       The registration, issue of certificate and inspection of magazine.

i.         The qualification, issue of certification and management of explosive manager.

j.        Other explosive related administrative, management and monitoring regulations.

2.      Governing agency at Municipal City under the direct jurisdiction of the Central Government:

a.       The required procedures according to company law and the regulations related to factory management and assistance.

b.      Jointly on-site inspection for the establishment of magazine.

c.       The inspection of explosive stolen and lose.

d.      Emergency handling of hazards caused by explosives.

e.       The monitoring, inspection and emergency measures for explosives and their manufacturing, sale and usage.

f.        Other items assigned by central governing agency.

 

Chapter two Manufacturing and sales

Article 6

The organizations of explosives manufacturing and sales is limited to the publicly owned company that are approved by Central Governing Agency and company established complied with company law.

Article 7

To conduct explosive manufacturing, the following documents need to be prepared for the application of permission to the Central Governing Agency, during its preparation or extending.

a.       Name of company and person.

b.      Administration plan.

c.       Engineering plan.

d.      Finance plan.

e.       Safety and emergency measures plan.

f.        The locations of planned business office and factory.

g.       Name and address of person in charge.

h.       Other items that need to be listed according to the regulations of Central Governing Agency.

Article 8

Besides the publicly owned company that is approved by Central Governing Agency, companies obtain the permission to prepare or extend explosive manufacturer should accomplish company registration or change of registration.  After the construction of factory and obtain factory registration, the required safety facility need also to be equipped according to requirements listed in Article 13 and inspected by Central Governing Agency before starting manufacturing.

The establishment of explosive factory described above should comply with the factory construction standard ruled by Central Governing Agency.

Article 9

Explosive manufacturer, after obtaining permission for establishing or extending factory, without obtaining factory registration certificate under no rational reason or stop manufacturing more than one year after the beginning of operation, the Central Governing Agency has the right to abolish its permission.

Article 10

To conduct explosive sales, the following documents need to be prepared for the application of permission to the Central Governing Agency, during its preparation or extending.

a.       Name of company and person.

b.      Administration plan.

c.       Structure and Safety facility for the planned sales location.

d.      Finance plan.

e.       Safety and emergency measures plan.

f.        The locations of planned business office and distribution office.

g.       Name and address of person in charge.

To establish sales distribution offices, the explosive seller should also apply for the permission from the Central Governing Agency.

Article 11

Explosive seller, after obtaining permission for preparing establishment, without conducting business under no rational reason or stop business for more than one year, the central governing agency has the right to abolish its permission.

Explosives seller, after obtaining permission to establish additional distributing office, without conducting business under no rational reason or stop business for more than one year, the Central Governing Agency has the right to abolish its permission.

Article 12

The purchaser of explosives is limited to those who obtain explosive purchase certificate complied with the regulations described in Article 14.

Article 13

The explosive manufacturers, seller (including distribution office) shall comply with the following requirements to establish safety facility.  After obtaining the approval from the Central Governing Agency, the manufacturing and operation can then be executed.  The operation or opening date shall be reported to the Central Governing Agency, Municipal Government at Municipal City under the direct jurisdiction of the Central Government and County and City Government at County and City.

 

1.   The explosive factory and sales location (including warehouse and distribution office) shall have on site security guard to secure safety.

2.   Setup safety regulations base upon actual condition and acquire approval from the Central Governing Agency.

3.   Assign specific department or person to handle personnel evaluation.

4.   Establish explosive magazine and guardhouse, and assign designated personnel or personnel shift.

5.   To coordinate with related governmental agencies to conduct necessary safety measures.

The facility for the manufacturing and sales of explosive materials shall restrict both employees and visitors to bring or take out explosive materials when enter or leave the facility.

The subparagraph1 in paragraph1 and above paragraph do not apply to on-site bulk blasting agents manufacturers.

 

Article 14

The explosives purchasers, besides explosives manufacturer and seller who posses the permission approved by Central Governing Agency, are limited to companies which conduct mining, exploration, sand and gravel excavation, civil engineering, construction, blasting manufacturing or tasks that is necessary to use explosives and approved by Central Governing Agency.

 

Explosive purchasers apply for purchasing quota should fill out application form and then apply for purchasing certificate from Central Governing Agency.

 

For engineering contractor tend to purchase explosive products, shall fill out the explosive purchase application form and obtain approval from the contracting company before fulfilling application requirements listed above.  The contracting company is responsible to monitor the usage of explosive of the contractor.

 

Chapter 3 Import, Export and Transportation

Article 15

For importing and exporting explosives, application form need to be prepared and apply for approval through Central Governing Agency, in which the type of explosives, quantities, import and export sea port and airport should be clearly listed.

Article 16

The transportation of explosive shall fill out application form for every shipment and apply for transportation certificate from Central Governing Agency.  The certificate for transportation of explosive within explosive factory, mines or construction sites can be exempted.

Article 17

The transportation of explosives shall assign specific vehicle and personnel and follow approved transportation route and schedule.  In addition, the following regulations shall also be followed.

1.      When transport through municipal area, transportation certificate shall submit to local police department and apply for the lead or traffic control.

2.      Transportation tools shall attach (hang) warning sign or flag.

3.      Detonators shall not, in any circumstance, be transported with low explosive, explosives or raw materials for manufacturing explosive in the same vehicle.

4.      The explosive packaging shall be sturdy, with internal padding for shock resistance.

5.      When park or unload explosive shall make sure brake is secured.  To park near gas station and flame source is highly restricted.

Chapter 4 Use, Storage and Handling

Article 18

The use of explosive shall be handle by trained blasting professional personnel and comply with the following regulations.

1.      The amount of explosive used should base upon the quantity estimated for daily use.  The unused explosives shall be returned to the magazine within 24 hours after removed from the magazine, but stored any other location besides magazine.  For special circumstance, it can be exempted after approved by Central Governing Agency.

2.      The handover of explosive shall select proper location outside of magazine.

3.      Explosive products and initiating products shall be stored in separate wooden, paper, plastic or any other non-electric conducted special containers and do not allow any non-explosive products exist in the same container.

4.      The charging and initiating of explosive shall be executed with safe method and apparatus.

5.      A wide-spreading warning and necessary safety security need to be done before initiation.

6.      After initiation, the remained un-initiated explosive shall be disposed through safe measures.

The above mentioned blasting professional trainee, training courses, training hours, issue of certificate and license, expiration date, reissue, abolishing and other regulations are ruled by Central Governing Agency.

Article 19

Explosives shall store in the magazine.  The quantity of explosive for daily used can be stored at the safe place in the job site under monitoring by assigned personnel.

Article 20

Explosive manufacturer, seller and purchasers shall establish magazine and guardhouse and assign designated personnel or personnel shift except for those who comply with paragraph 21 and obtain permission.

Article 21

For explosive seller and purchasers, the location of storage and use of explosive near others’ magazine, the explosives can be stored in others’ magazine after obtained the permission from Central Governing Agency.

Article 22

For establishment or change of magazine, an application need to be filed for the inspection conducted jointly by Central Governing Agency and authorities of Municipal City under the direct jurisdiction of the Central Government and County and City Government at County and City and obtain permission.

After the construction of magazine and before its use, the magazine need to be inspected jointly by Central Governing Agency and authorities of Municipal City under the direct jurisdiction of the Central Government and County and City Government at County and City and obtain permission.